The Kawartha Lakes Record

Committee of Adjustment

March 17, 2022

What was decided (15 motions)

12 carried, 3 recorded otherwise. Every motion below is printed as the minutes print it.

That the agenda for March 17, 2022 meeting be approved.
Moved by B. Archer, seconded by S. Richardson
Carried
That the minutes of the previous meeting held February 17, 2022 be adopted as printed.
Moved by S. Strangway, seconded by D. Marsh
Carried
That Minor Variance Application D20-2021-077 be
Moved by D. Marsh, seconded by B. Archer
Deferred
That minor variance application D20-2022-010 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. Conditions: That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C and generally in accordance with the sketches in Appendix D submitted as part of Report COA2022-017, which shall be attached to and form part of the Committee’s Decision. That the Secretary-Treasurer receive confirmation from Building and Septic Division-Supervisor, Part 8 Sewage Systems, that should a septic approval be required, that it be obtained. This approval pertains to the application as described in report COA2022-017. Fulfillment of all conditions is required for the Minor Variances to be considered final and binding.
Moved by B. Archer, seconded by S. Richardson
Carried
That minor variance application D20-2022-011 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. Conditions: That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C submitted as part of Report COA2022-018, which shall be attached to and form part of the Committee’s Decision; and That the building construction related to the minor variances shall be completed within a period of eight (8) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection. This approval pertains to the application as described in report COA2022-018. Fulfillment of all conditions is required for the Minor Variances to be considered final and binding.
Moved by S. Strangway, seconded by B. Archer
Carried
That minor variance application D20-2022-012 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. Conditions: That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C and elevations in Appendix D submitted as part of Report COA2022-019, which shall be attached to and form part of the Committee’s Decision; That prior to the issuance of the building permit for the cabin, the owner shall submit photographic evidence to the satisfaction of the Secretary-Treasurer demonstrating the building identified as “Shed” in Appendix C to Report COA2022-019 is used as a shed; and That the building construction related to the minor variances shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection. This approval pertains to the application as described in report COA2022-019. Fulfillment of all conditions is required for the Minor Variances to be considered final and binding.
Moved by S. Richardson, seconded by Councillor Yeo
Carried
That Minor variance Application D20-2022-013 be
Moved by D. Marsh, seconded by B. Archer
Deferred
That minor variance application D20-2022-016 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. Conditions: That the building construction related to this approval shall proceed generally in accordance with the landscape plan in Appendix C and elevations in Appendix D submitted as part of Report COA2022-021, which shall be attached to and form part of the Committee’s Decision; and That the site plan agreement shall be registered within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This approval pertains to the application as described in report COA2022-021. Fulfillment of all conditions is required for the Minor Variances to be considered final and binding.
Moved by S. Richardson, seconded by S. Strangway
Carried
That minor variance application D20-2022-017 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. Conditions: That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C and elevations in Appendix D submitted as part of Report COA2022-022, which shall be attached to and form part of the Committee’s Decision; and That the building construction related to the minor variance shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection. This approval pertains to the application as described in report COA2022-022. Fulfillment of all conditions is required for the Minor Variance to be considered final and binding.
Moved by S. Strangway, seconded by D. Marsh
Carried
That minor variance application D20-2022-018 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. Conditions: That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C submitted as part of Report COA2022-023, which shall be attached to and form part of the Committee’s Decision; and That the building construction related to the minor variances shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection. This approval pertains to the application as described in report COA2022-023. Fulfillment of all conditions is required for the Minor Variance to be considered final and binding.
Moved by D. Marsh, seconded by B. Archer
Carried
That the meeting be adjourned at 4:27pm.
Moved by D. Marsh, seconded by S. Richardson
Carried
6 That Minor Variance Application D20-2021-077 be
Moved by D. Marsh, seconded by B. Archer
Deferred
That minor variance application D20-2022-011 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. Conditions: 1. That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C submitted as part of Report COA2022-018, which shall be attached to and form part of the Committee’s Decision; and 2. That the building construction related to the minor variances shall be completed within a period of eight (8) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This 11 condition will be considered fulfilled upon completion of the first Building Inspection. This approval pertains to the application as described in report COA2022- 018. Fulfillment of all conditions is required for the Minor Variances to be considered final and binding.
Moved by S. Strangway, seconded by B. Archer
Carried
That minor variance application D20-2022-012 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. Conditions: 1. That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C and elevations in 13 Appendix D submitted as part of Report COA2022-019, which shall be attached to and form part of the Committee’s Decision; 2. That prior to the issuance of the building permit for the cabin, the owner shall submit photographic evidence to the satisfaction of the Secretary-Treasurer demonstrating the building identified as “Shed” in Appendix C to Report COA2022-019 is used as a shed; and 3. That the building construction related to the minor variances shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection. This approval pertains to the application as described in report COA2022- 019. Fulfillment of all conditions is required for the Minor Variances to be considered final and binding.
Moved by S. Richardson, seconded by Councillor Yeo
Carried
That minor variance application D20-2022-017 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. Conditions: 1. That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C and elevations in Appendix D submitted as part of Report COA2022-022, which shall be attached to and form part of the Committee’s Decision; and 2. That the building construction related to the minor variance shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection. 17 This approval pertains to the application as described in report COA2022- 022. Fulfillment of all conditions is required for the Minor Variance to be considered final and binding.
Moved by S. Strangway, seconded by D. Marsh
Carried

The town’s own record

Read the minutes this page was read from →

Where this page and that document disagree, the document is right and this record is wrong. Say so and it will be corrected.