Everything on this site is searchable — a file number, a councillor, a motion, a meeting, or an application.
Committee of Adjustment
April 21, 2022
What was decided (15 motions)
15 carried, 0 recorded otherwise. Every motion below is printed as the minutes print it.
That the agenda for April 21, 2022 meeting be approved as amended.
Moved by S. Strangway, seconded by B. Archer
Carried
That the minutes of the previous meeting held March 17, 2022 be adopted as printed.
Moved by D. Marsh, seconded by B. Archer
Carried
That minor variance application D20-2022-004 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. Conditions: That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C and elevations in Appendix D submitted as part of Report COA2022-024, which shall be attached to and form part of the Committee’s Decision, That the building construction related to the minor variances shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection. This approval pertains to the application as described in report COA2022-024. Fulfillment of all conditions is required for the Minor Variances to be considered final and binding.
Moved by D. Marsh, seconded by J. Robinson
Carried
That minor variance application D20-2022-014 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. Conditions: That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C and elevations in Appendix D submitted as part of Report COA2022-025, which shall be attached to and form part of the Committee’s Decision; and That the building construction related to the minor variances shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection. This approval pertains to the application as described in report COA2022-025. Fulfillment of all conditions is required for the Minor Variances to be considered final and binding.
Moved by S. Strangway, seconded by B. Archer
Carried
That minor variance application D20-2022-020 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. Conditions: That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C and elevations in Appendix D submitted as part of Report COA2022-026, which shall be attached to and form part of the Committee’s Decision; and That the building construction related to the minor variance shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection. This approval pertains to the application as described in report COA2022-026. Fulfillment of all conditions is required for the Minor Variance to be considered final and binding.
Moved by J. Robinson, seconded by D. Marsh
Carried
That minor variance application D20-2022-021 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. Conditions: That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C and elevations in Appendix D submitted as part of Report COA2022-027, which shall be attached to and form part of the Committee’s Decision; That the driveway be revised to conform with the Lot Grading and Drainage Plan and comply with the provisions of the Zoning By-Law Section 5.12 (j) (x): and That the building construction related to the minor variances shall be completed within a period of six (6) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection. This approval pertains to the application as described in report COA2022-027. Fulfillment of all conditions is required for the Minor Variance to be considered final and binding.
Moved by J. Robinson, seconded by D. Marsh
Carried
That minor variance application D20-2022-022 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. Conditions: That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C and generally in accordance with the elevations in Appendix D submitted as part of Report COA2022-028, which shall be attached to and form part of the Committee’s Decision; and That the building construction related to the minor variances shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection. This approval pertains to the application as described in report COA2022-028. Fulfillment of all conditions is required for the Minor Variances to be considered final and binding.
Moved by B. Archer, seconded by S. Richardson
Carried
That minor variance application D20-2022-015 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. Conditions: That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C and elevations in Appendix D submitted as part of Report COA2022-029, which shall be attached to and form part of the Committee’s Decision; and That the building construction related to the minor variance shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection. This approval pertains to the application as described in report COA2022-029. Fulfillment of all conditions is required for the Minor Variance to be considered final and binding.
Moved by S. Strangway, seconded by J. Robinson
Carried
That minor variance application D20-2022-013 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. Conditions: That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C and elevations in Appendix D submitted as part of Report COA2022-020, which shall be attached to and form part of the Committee’s Decision; and That the building construction related to the minor variance shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection. This approval pertains to the application as described in report COA2022-020. Fulfillment of all conditions is required for the Minor Variance to be considered final and binding.
Moved by D. Marsh, seconded by B. Archer
Carried
That the meeting be adjourned at 3:02pm.
Moved by D. Marsh, seconded by J. Robinson
Carried
That minor variance application D20-2022-004 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. Conditions: 4 1. That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C and elevations in Appendix D submitted as part of Report COA2022-024, which shall be attached to and form part of the Committee’s Decision, 2. That the building construction related to the minor variances shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection. This approval pertains to the application as described in report COA2022- 024. Fulfillment of all conditions is required for the Minor Variances to be considered final and binding.
Moved by D. Marsh, seconded by J. Robinson
Carried
That minor variance application D20-2022-020 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. 7 Conditions: 1. That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C and elevations in Appendix D submitted as part of Report COA2022-026, which shall be attached to and form part of the Committee’s Decision; and 2. That the building construction related to the minor variance shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection. This approval pertains to the application as described in report COA2022- 026. Fulfillment of all conditions is required for the Minor Variance to be considered final and binding.
Moved by J. Robinson, seconded by D. Marsh
Carried
That minor variance application D20-2022-022 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. Conditions: 1. That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C and generally in accordance with the elevations in Appendix D submitted as part of Report COA2022-028, which shall be attached to and form part of the Committee’s Decision; and 11 2. That the building construction related to the minor variances shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection. This approval pertains to the application as described in report COA2022- 028. Fulfillment of all conditions is required for the Minor Variances to be considered final and binding.
Moved by B. Archer, seconded by S. Richardson
Carried
That minor variance application D20-2022-015 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. Conditions: 1. That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C and elevations in 12 Appendix D submitted as part of Report COA2022-029, which shall be attached to and form part of the Committee’s Decision; and 2. That the building construction related to the minor variance shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection. This approval pertains to the application as described in report COA2022- 029. Fulfillment of all conditions is required for the Minor Variance to be considered final and binding.
Moved by S. Strangway, seconded by J. Robinson
Carried
That minor variance application D20-2022-013 be GRANTED, as the application meets the tests set out in Section 45(1) of the Planning Act. Conditions: 1. That the building construction related to this approval shall proceed substantially in accordance with the sketch in Appendix C and elevations in Appendix D submitted as part of Report COA2022-020, which shall be attached to and form part of the Committee’s Decision; and 2. That the building construction related to the minor variance shall be completed within a period of twenty-four (24) months after the date of the Notice of Decision, failing which this application shall be deemed to be refused. This condition will be considered fulfilled upon completion of the first Building Inspection. This approval pertains to the application as described in report COA2022- 020. Fulfillment of all conditions is required for the Minor Variance to be considered final and binding. 14